Alpha Compute Corp Closes On Acquisition Of 321 Acre Data Center Campus Site With 430 MW Of Natural Gas Power In Elk County; Petition Calls For Strong Local Regulation In Community Of 1,569 People

Posted
On November 19, the
Alpha Compute Corp. announced it had closed a $5.5 million acquisition of assets to develop the Alpha Energy 02 Data Center Campus and power facilities in Jones Township, Elk County.

The campus includes 321 surface acres, 87 shallow [conventional] oil and natural gas wells, together with undeveloped natural gas and mineral rights beneath the property, including Marcellus and Utica shale formations. 

The assets also include the pump jack inventory, maintenance facilities, heavy equipment and gathering infrastructure.

Oil production and sales are expected to start once the Department of Environmental Protection approves the Company as the operator. 

Once the first data center designs are final, Alpha Compute expects to offer future data center capacity and power purchase agreements.

The campus includes 321 surface acres, 87 shallow oil and natural gas wells, together with undeveloped natural gas and mineral rights beneath the property, including Marcellus and Utica shale formations. 

The assets also include the pump jack inventory, maintenance facilities, heavy equipment and gathering infrastructure.

Alpha Energy 02 plans to use the campus's natural gas as fuel for its own on-site power, in phases: an LNG microgrid first, moving to natural gas produced on site as development proceeds, using the same generation equipment. 

The first 10 megawatts would be immediately online within nine months, with a build-out toward 200 megawatts within 18 months or less.

Visit the Alpha Compute website for more information.

Petition Calls For Strong Local Regulation Of Data Centers

On November 23, a petition was posted on Change.org calling on Jones Township and Elk County Commissioners to oppose the project and immediately pursue adopting a local data center ordinance to regulate data center developments.

The petition description notes the project “is located within the headwater region of the Clarion River watershed. The East Branch Clarion River basin is designated by Pennsylvania as a High Quality Cold Water Fishery and receives additional environmental protections under state law.

“Our interconnected waterways, including Swamp Creek, East Branch Clarion River Lake and the Clarion River, support Glen Hazel, Bendigo State Park, Johnsonburg, Ridgway and other downstream communities.”

“Jones Township currently has no zoning ordinance and relies on a Subdivision and Land Development Ordinance (SALDO).

“As of November 22, 2026, no formal development or permit applications have reportedly been submitted to the township.”

“Under Pennsylvania law, once a land development application is properly filed, the township’s ability to apply newly adopted regulations may become limited.

“We have a critical opportunity to establish meaningful protections before that happens.

“The absence of zoning is not a justification for inaction. It is a compelling reason for immediate action.

“We call upon the Jones Township Board of Supervisors, Elk County Commissioners and appropriate regulatory authorities to:

-- Formally oppose the Alpha Energy 02 Campus and exercise all available legal authority to prevent its approval where warranted.

-- Immediately pursue comprehensive zoning, strengthen the existing SALDO, adopt supplemental protective ordinances and evaluate lawful interim development restrictions.

-- Require independent environmental, hydrological, public health and infrastructure assessments addressing the cumulative impacts of the entire development and its future expansion.

-- Protect private wells, groundwater, headwaters and downstream communities through water withdrawal restrictions, baseline testing, ongoing monitoring and developer-funded remediation of attributable damages.-- Establish enforceable standards for noise, emissions, lighting, setbacks, water consumption, stormwater management and industrial safety.

-- Make the developer’s publicly stated environmental commitments legally enforceable, rather than relying on voluntary corporate promises.

-- Protect residents and taxpayers from costs associated with industrial development, infrastructure improvements, emergency services and environmental damage.

-- Convene a special public meeting, establish an expedited timeline for ordinance adoption and ensure full transparency and meaningful participation by all affected communities.

-- All regulatory measures should be pursued to the fullest extent permitted by law.

Click Here for more information on the petition.   Click Here for media inquiries through Change.org.

As of November 23, the petition had 530 signatures. Jones Township has a population of 1,569 and Elk County has a population of 30,990.

Elk County Commissioners

On November 20, Elk County Commissioners posted this statement on its Facebook page--

First and foremost, the commissioners want to assure the public that the health, safety, and well-being of Elk County residents are of paramount importance. 

Regardless of the issue, we remain committed to being actively engaged whenever an activity has the potential to affect our communities or our quality of life. 

That commitment does not change based on the size of a challenge or the financial resources behind it. 

Our communities and our way of life are simply too important for us to expect anything less.

At the same time, it is important to understand the respective roles and responsibilities of county and municipal government in Pennsylvania. 

County government does not exercise authority over local municipalities in a traditional top-down structure. 

Rather, locally elected municipal officials have primary responsibility for governing the people and land within their respective jurisdictions, consistent with applicable state law.

This distinction does not mean the county cannot serve as a partner to locally elected officials. 

We can provide technical or financial assistance where available, share information, and help communicate a unified message to state and federal policymakers when appropriate. 

However, the authority of local municipalities to govern matters within their jurisdictions is a fundamental principle of our Commonwealth's system of government.

The Elk County Commissioners have enjoyed a longstanding and positive working relationship with township supervisors throughout the county, including those serving Jones Township. 

We have already had several discussions with the Jones Township Supervisors and have provided them with a letter expressing our interest in the proposed development and requesting that we be kept informed of future updates, discussions, and filings.

Should the Jones Township Supervisors wish to involve the county commissioners further, we stand ready to provide whatever assistance is available to us and to serve as a partner in their efforts. 

This may include acting as a liaison, as needed, to facilitate and foster discussions among state and local representatives, including Senator Dush, Representative Armanini, and Congressman Thompson, the Pennsylvania Department of Environmental Protection (DEP), the Pennsylvania Utility Commission (PUC), Elk County Planning Department resources, consultants, and other relevant parties.

Finally, we appreciate everyone who has taken the time to contact our office and share their questions, concerns, and perspectives regarding the potential impacts of this proposed data center. 

Please know that these comments are taken seriously and will be considered as we continue our efforts to preserve what makes Elk County special: a beautiful place to visit, a welcoming community, and a great place to call home.

Visit the Elk County Commissioners webpage for more information.

[Posted: November 24, 2026]  PA Environment Digest